Poland, express lane

Eurovia Polska builds a 14-km section of the expressway linking Warsaw and Gdansk

This is the largest project ever undertaken by Eurovia Polska: to build a 14-km section of the S7 Gdansk-Warsaw expressway between Elblag and Kalsk. The contract was signed in October 2008 by the consortium consisting of Eurovia Polska (leader), Eurovia Verkehrsbau Union, Warbud (VINCI Construction), Ol-Trans and Drogomex. The project is scheduled to take 22 months to complete excluding the winter months.

Key figures:

1.3 million metres of ballasted columns

1.5 million cubic metres of earthworks

13 engineering structures

280,000 tonnes of asphalt mix